President Netumbo Nandi-Ndaitwah has revealed that the Namibian government nearly lost a multibillion-dollar investment from Nigerian industrialist Aliko Dangote due to administrative delays. Speaking at the launch of the Dangote Namibia Tank Farm and Regional Pipeline Project on 4 November 2026, the President admitted that she had to directly communicate with Dangote to prevent him from abandoning the venture.
The project, valued at approximately US$2.5 billion (N$41.1 billion), involves a 600-million-litre fuel storage facility and a regional pipeline network spanning roughly 1,700 kilometres. It is designed to connect Namibia with Botswana, Zambia, Zimbabwe, and the Democratic Republic of Congo, positioning Walvis Bay as a regional energy hub.
Nandi-Ndaitwah acknowledged the frustrations experienced by the investor’s team and apologised for the delays. She stated that she placed the project directly under the Office of the President, directing National Planning Commission Director General Ambassador Kaire Mbuende to oversee implementation and report progress directly to her.
A Recurring Administrative Challenge
The President’s intervention highlights a systemic issue that has plagued successive Namibian administrations. She noted that her experience as minister of international relations and trade included losing a serious shipyard proposal after four years of bureaucratic hurdles. Although she did not disclose the investors' identities or the specific financial value of that lost project, she used it to illustrate the economic cost of prolonged administrative processes.
This pattern of inefficiency has been publicly criticised by previous leaders. In June 2006, former President Hifikepunye Pohamba reprimanded senior officials for poor implementation, warning that managers would be held accountable for unused development funds. He highlighted that government service providers were sometimes waiting up to three months for payment, which damaged relationships and suspended essential services.
Twelve years later, in February 2018, former President Hage Geingob linked bureaucratic bottlenecks to Namibia’s declining standing in global competitiveness rankings. He directed then Prime Minister Saara Kuugongelwa-Amadhila to conduct an audit of bureaucratic impediments and expedite reforms to improve the investment climate.
Independent Assessments Confirm Delays
The concerns raised by the President are supported by independent data regarding public project implementation. The African Development Bank’s Namibia Country Portfolio Performance Review 2025, published in February 2026, identified procurement and implementation delays as major challenges. The report noted that the period between project approval and the first disbursement of funds increased from 10.4 months to 13.6 months, largely due to prolonged procurement processes and additional clearance requirements from the Office of the Attorney General.
The review also highlighted specific operational hurdles affecting development projects:
- Lengthy bid evaluations that stall project initiation
- Procurement capacity constraints within government institutions
- Delays in contract clearance and additional legal requirements
Furthermore, the Bank reported that only 38% of targeted outcomes and 33% of planned outputs under Namibia’s 2020–2024 Country Strategy Paper had been achieved. The underperformance was attributed to incomplete projects and those that failed to materialise following changes in government priorities.
Economic Consequences and Future Outlook
For an economy seeking diversification and industrialisation, such delays carry significant consequences. When investors withdraw, Namibia loses potential capital, employment opportunities, business contracts, tax revenues, and skills transfer. The Dangote investment, expected to take 18 to 20 months to complete, represents a critical opportunity for employment and skills development, with the President emphasising that Namibians should be prioritised in its execution.
The African Development Bank did record some improvements in portfolio performance, noting that the proportion of red-flagged projects fell from 46% to 33% between July 2024 and March 2025. However, the persistence of these issues raises questions about the scalability of presidential interventions. If a project of this magnitude requires the President’s personal attention to proceed, smaller investors without access to the highest office may face insurmountable barriers. The government has called on the ministry of industries, mines and energy to address these systemic inefficiencies to ensure Namibia remains a competitive investment destination.