CPBN defends Windhoek hospital contract amid representation dispute

Key Takeaways

  • The Central Procurement Board of Namibia (CPBN) signed the N$174 million infrastructure contract on 12 November 2026 without prior notification of changes to the joint venture's authorized representation.
  • Jiangsu Shangsheng Construction submitted a letter dated 18 September withdrawing Kenneth Shikongo's authority, but this was not formally received by the board until 16 November.
  • Construction activities began on 16 November after the site was handed over, with no payment claims or payments made as of 20 November.
  • The board instructed the joint venture partners to resolve their differences and communicate their position by 23 November 2026.
  • The contract covers bulk earthworks and essential infrastructure including water reservoirs, access roads, and sewerage systems for the planned hospital.

The Central Procurement Board of Namibia (CPBN) has firmly defended the validity of a N$174 million infrastructure contract for the planned Windhoek District Hospital, asserting that it acted on accurate documentation at the time of signing. The board clarified that it had not been formally notified of any changes to the joint venture’s authorized representation before the agreement was executed on 12 November 2026.

Johanna Kambala, the board’s spokesperson, stated that Kenneth Shikongo was designated as the joint venture’s authorized representative through a power of attorney submitted during the initial bidding process. Consequently, the board proceeded with the contract signing based on the records available to it. The controversy arose after Jiangsu Shangsheng Construction reportedly disowned Shikongo, who presented himself as their representative at the signing ceremony.

The board received correspondence from Jiangsu Shangsheng Construction concerning the alleged withdrawal of Shikongo’s authority on 16 November, four days after the contract was signed. Although the correspondence was dated 18 September, Kambala emphasized that it had not been formally submitted to the CPBN prior to the execution of the agreement.

Joint Venture Dispute Resolution

Following the emergence of the dispute, the CPBN convened a meeting on 18 November with representatives from both joint venture partners and their legal counsel. During this session, Jiangsu Shangsheng confirmed that its letter withdrawing Shikongo’s authority had been communicated to its partner, Elderwood Trading CC, but had not been formally submitted to the procurement board at the time of the contract signing.

The board held the joint venture partners accountable for maintaining the accuracy and authenticity of documents submitted during the procurement process. It reiterated that any subsequent changes affecting a joint venture’s composition, legal representation, or authorization must be formally communicated to the board to ensure transparency and legal compliance.

The CPBN directed the two companies to resolve their internal differences and formally communicate their position and proposed way forward to the board. The deadline for this resolution was set for Monday, 23 November 2026. The board stressed that bidders, particularly those participating in joint ventures, bear the responsibility for ensuring all submitted documentation remains current and accurate throughout the procurement lifecycle.

Project Implementation Status

Despite the administrative controversy, the CPBN rejected suggestions that the hospital project had been suspended. Kambala confirmed that the construction site was officially handed over to the contractor on 16 November, and construction activities commenced on the same day. This indicates that physical work on the ground has proceeded independently of the legal representation dispute between the partners.

As of 20 November, the board reported that no payment claims had been submitted by the contractor, and consequently, no payments had been made. This status reflects that implementation had only recently started, and financial transactions are contingent upon the submission of valid claims as per the contract terms.

The contract was awarded to Elderwood Trading CC in a joint venture with Jiangsu Shangsheng Construction following an open national bidding process. The N$174 million agreement covers bulk earthworks and essential infrastructure services for the planned hospital. These services include the construction of a water reservoir, access roads, stormwater drainage systems, water supply networks, sewerage infrastructure, and electricity infrastructure.

Clarification of Signatories

In addition to addressing the representation dispute, the CPBN issued a correction regarding its previous media release. The board acknowledged an error in its 13 November statement, which had incorrectly identified Huang Heng Wan as a representative of Jiangsu Shangsheng Construction.

Kambala clarified that Huang attended the signing ceremony as an engineer affiliated with Elderwood Trading CC. He was not a signatory to the contract nor an authorized signatory for Jiangsu Shangsheng. The contract was officially signed by Mr. Kenneth Shikongo, the designated authorized representative of the joint venture, and witnessed by Mr. Mathias Shipale.

The board emphasized that all parties involved in public procurement must adhere strictly to the documentation submitted during the bidding phase. Any deviations or changes in authorized personnel must be formally reported to prevent such discrepancies in the future. The CPBN remains focused on ensuring the timely and efficient delivery of the Windhoek District Hospital infrastructure while maintaining the integrity of the procurement process.

Sources & Attributions

This synthesis is compiled from reporting by the following independent publications:

Editorial Notice on Media Use: Pictures on this page illustrate the news and carry their credit where one is held. No copyright ownership is claimed. Our editorial policy says how pictures are chosen.

More in Policy & Regulation