Land approval delays stall Namibia's telecom infrastructure rollout

Key Takeaways

  • Telecommunications land applications in Namibia are facing approval delays of up to two years, disrupting infrastructure development plans.
  • The minister highlighted that maintenance teams are often denied access to commercial farms, compromising network reliability in remote regions.
  • Constructing a single telecommunications tower costs between N$2.8 million and N$3.5 million, with theft and vandalism adding further financial pressure.
  • New towers are planned for Nordower and Hakiesdoorn in the Karasburg West constituency through the Universal Service Access Fund.

Information and Communication Technology Minister Emma Theofelus has identified prolonged land approval processes as a primary obstacle to expanding telecommunications infrastructure across Namibia. Speaking at a high-level stakeholder engagement in the //Kharas Region, she noted that applications involving traditional authorities, local councils, and commercial farm owners can remain pending for as long as two years.

These administrative delays are directly impacting the government’s objective to achieve 100% population network coverage by 2030. Theofelus explained that the lengthy waiting periods often exceed the standard 12-month financial year, leaving operators with insufficient time to complete essential environmental assessments, procurement procedures, and construction work within the allocated budget cycles.

When approvals are delayed, government entities and service providers are frequently forced to redirect available funding to alternative locations where land rights have already been secured. This reallocation leaves many rural communities without the improved network coverage they were promised, disrupting the utilisation of funds designated for digital inclusion.

Access issues and maintenance challenges

Beyond administrative hurdles, the minister raised serious concerns regarding physical access to existing infrastructure situated on private commercial farms. She reported that in regions such as Karas, property owners are occasionally preventing maintenance teams from entering their premises to service equipment. In some instances, technical teams have been locked out, rendering them unable to repair or maintain the expanded network.

These restrictions undermine the reliability of telecommunications services in remote areas. Theofelus emphasized that without cooperation from farm owners and local authorities, it is impossible to ensure consistent service delivery. She urged all stakeholders, including traditional leaders and regional councils, to expedite approval processes and facilitate access for maintenance crews to support the sector’s growth.

Financial pressures and infrastructure costs

The economic burden of maintaining and expanding the network is significant. Theofelus disclosed that the cost to construct a single telecommunications tower ranges from N$2.8 million to N$3.5 million, depending on the specific location and the need for alternative power supplies where electricity is unavailable.

Compounding these construction costs is the persistent issue of theft and vandalism targeting telecommunications equipment. Solar panels and batteries are frequently stolen, placing additional financial strain on operators. Funds that could otherwise be deployed to extend network coverage are increasingly being diverted toward replacing damaged or stolen components, slowing the overall pace of rural connectivity.

Targeted interventions in underserved areas

Despite these challenges, the ministry has identified specific locations for immediate intervention. Theofelus announced that new telecommunications towers will be constructed in Nordower and Hakiesdoorn, located in the Karasburg West constituency. These projects are being funded through the Universal Service Access Fund, which is dedicated to improving connectivity in underserved communities.

The minister called for improved coordination between the government, local communities, and network operators. She stressed that addressing administrative delays and ensuring access to infrastructure are critical steps required to accelerate the rollout of telecommunications services. The ongoing efforts aim to bridge the digital divide and ensure that rural populations benefit from the national connectivity targets.

Key factors affecting the rollout include:

  • Land approval processes that can take up to two years, exceeding financial year cycles.
  • Maintenance teams being locked out of commercial farms, disrupting service reliability.
  • Construction costs for single towers ranging from N$2.8 million to N$3.5 million.
  • Funds being diverted from expansion to replace stolen solar panels and batteries.
  • New towers planned for Nordower and Hakiesdoorn via the Universal Service Access Fund.

Sources & Attributions

This synthesis is compiled from reporting by the following independent publications:

Editorial Notice on Media Use: Pictures on this page illustrate the news and carry their credit where one is held. No copyright ownership is claimed. Our editorial policy says how pictures are chosen.

More in Enterprise & SMEs