Namibia’s housing infrastructure agenda has encountered significant bottlenecks, with the Ministry of Urban and Rural Development admitting that not a single fully serviced residential plot has been handed over under its current multi-billion dollar initiative. The programme, which aims to provide basic utilities to 17,000 sites, remains stalled due to a lack of available capital, leaving thousands of potential homes without the essential water, sewerage, electricity, and road networks required for habitation.
Urban and Rural Development Minister James Sankwasa responded to parliamentary inquiries by confirming that while infrastructure works are underway at various stages, none have reached the point of full serviceability. He highlighted that the Ministry’s allocated capital budget of N$1.2 billion for the 2025/26 financial year falls drastically short of the financial requirements needed to complete bulk infrastructure projects. This funding gap is the primary obstacle preventing the delivery of plots in informal settlements, where residents cannot afford the high costs of infrastructure development, leaving the state as the sole financier.
Funding Constraints and Geographic Spread
The scope of the stalled land servicing programme is extensive, covering major urban centers and regional hubs. The government’s inability to meet delivery timelines is directly linked to the reliance on state funding for projects located in areas where low-income households reside. Sankwasa emphasized that the bulk of the targeted land servicing occurs in informal settlements, creating a financial burden on the Ministry that current budgets cannot sustain.
The initiative spans a wide geographic area, with specific plot allocations assigned to various municipalities. The distribution of the 17,000 targeted plots includes:
- 5,000 plots designated for Windhoek
- 1,200 plots each for Walvis Bay, Keetmanshoop, Rundu, and Oshakati
- 1,200 plots each for Usakos, Bukalo, Katima Mulilo, Mariental, Otjiwarongo, and Swakopmund
Despite the lack of serviced land, the Ministry has maintained momentum in actual housing construction. During the 2025/26 financial year, 1,112 housing units were completed, with the majority arising from new developments rather than upgrading existing informal structures. The delivery of these units continued into the 2026/27 financial year, with 846 units finished in the first quarter and 725 in the second, bringing the cumulative total to 2,683 units across both periods.
Housing Delivery Statistics and Future Targets
The distinction between land servicing and housing construction remains critical in assessing the ministry's performance. While the former is delayed, the latter has seen varied success depending on the source of the units. The Shack Dwellers Federation of Namibia (SDFN) played a substantial role in the housing delivery figures, particularly through initiatives focused on upgrading informal settlements and building new homes in various regions.
Minister Sankwasa clarified misconceptions regarding official housing targets, correcting a parliamentary reference that suggested a goal of 10,000 houses. He stated that the official target for the 2025/26 financial year was set at 3,000 units. The Ministry is currently working to secure additional funding and streamline procurement processes to accelerate both land servicing and housing delivery.
Looking ahead, the Ministry has set specific completion dates for ongoing projects. Infrastructure and servicing works are expected to be finalized by December 2026, although the Minister acknowledged that funding constraints continue to threaten this timeline. Additionally, 304 housing units under construction at Otjomuise Extension 10 in Windhoek are scheduled for completion by the end of December 2026.
Institutional Reforms and Procurement
In response to questions regarding the administrative structure of housing delivery, Sankwasa addressed calls to restructure the former Township Board. He confirmed that no such restructuring is necessary because the entity was already dissolved and replaced by the Urban and Regional Planning Board under the Urban and Regional Planning Act of 2018. This new board consolidated the functions of both the former Namibia Planning Authority Board and the Township Board, streamlining regulatory oversight.
The Ministry is currently in the procurement stage for 174 housing units, with the majority located in Swakopmund. These units are targeted for completion before the end of the current financial year, alongside projects in Walvis Bay and Mariental. Sankwasa stated that the Ministry is strengthening its internal project management capacity to ensure that future targets are met despite the challenging financial environment. The focus remains on prioritizing land servicing in informal settlements occupied by ultra-low- and low-income households, where inadequate infrastructure continues to be the primary barrier to housing development.
Operational Challenges in Informal Settlements
The core of the Ministry’s challenge lies in the economic reality of the communities it serves. Sankwasa noted that people in the targeted informal areas grapple with affordability challenges, making private sector involvement in infrastructure development unviable. Consequently, the government must bear the full cost of providing bulk services, a task that is becoming increasingly difficult as cash-flow constraints persist.
The Ministry continues to grapple with attaining its set targets on account of these cash flow challenges. By focusing on institutional reforms and seeking additional funding sources, the government aims to overcome the stagnation in land servicing. Until the capital budget is increased or alternative financing is secured, the delivery of fully serviced plots is likely to remain delayed, even as housing construction units continue to be delivered through separate initiatives.