The Namibian Ports Authority (Namport) has firmly rejected recent reports suggesting that congestion at the Port of Walvis Bay is responsible for a series of skipped vessel calls. The authority stated that the port is not experiencing the bottlenecks alleged by some observers and remains fully equipped to manage increased cargo volumes.
Instead of internal inefficiencies, Namport attributed the recent disruptions to strategic decisions made by international shipping lines. These carriers are implementing schedule recovery measures to restore reliability after encountering delays at earlier ports along their routes. This practice involves skipping specific ports to protect downstream berthing windows within established service rotations.
Upstream Delays Drive Schedule Changes
Namport provided detailed timelines for three specific vessels to illustrate how delays at previous ports impacted their arrival in Namibia. The authority highlighted that these adjustments were necessary for carriers to maintain schedule integrity across their networks.
The MAERSK SYDNEY was originally scheduled to arrive in Walvis Bay on November 9. However, the vessel did not depart from Luanda, Angola, until November 10. This one-day delay pushed its revised arrival date back to November 14 before it even entered Namibian waters.
Similarly, the APL SANTIAGO was scheduled to depart Luanda on November 18, with an original arrival in Walvis Bay planned for November 20. Adjustments to this timeline would have caused the APL SANTIAGO to arrive almost simultaneously with its sister vessel, the APL MIAMI, which had a revised arrival date of November 23. Such simultaneous arrivals could strain port resources, prompting the skip.
The COSCO KOREA, due in Walvis Bay on November 27, also faced significant shifts. Its departure from Luanda was pushed back to December 1 due to earlier delays. Consequently, its arrival in Namibia was delayed until roughly December 7, leading to its omission from the immediate schedule.
Protocol Disputes and Operational Efficiency
Beyond the schedule adjustments driven by upstream issues, Namport addressed the omission of the Blue Master II. The vessel arrived behind schedule from its previous port and subsequently requested priority berthing ahead of other ships already waiting in line.
Namport stated that standard operational protocols prevented the authority from granting this request. When the carrier did not receive the preferred treatment, it opted to sail directly to its next stop in Cape Town rather than wait its turn.
Commercial executive Elias Mwenyo reiterated the authority's commitment to maintaining efficient operations. He emphasized Namport's goal of positioning Namibia as Africa’s leading maritime logistics hub, reassuring the business community that the port remains capable and reliable despite external scheduling challenges.
Key factors in the recent vessel skipages include:
- The MAERSK SYDNEY missing its November 9 arrival due to a late departure from Luanda on November 10.
- The APL SANTIAGO being omitted to avoid a simultaneous arrival with the APL MIAMI on November 23.
- The COSCO KOREA’s arrival delayed from November 27 to early December due to a late departure from Luanda on December 1.
- The Blue Master II skipping Walvis Bay after its request for priority berthing was denied under standard protocols.
Namport maintained that these actions were taken by the shipping lines themselves to protect their broader network reliability. The authority stressed that the port infrastructure is not the limiting factor in these disruptions.